The contribution would allow the construction work to continue while the claims are resolved under the mechanisms established within the contract.
ACP has proposed to advance US$100m to GUPC to allow the contractor to tend to its pending obligations. The contractor must agree these funds through a letter of credit. In addition, ACP is willing to extend the moratorium for the repayment of US$83m in advances by GUPC for two months, leaving that money free for capital injection.
However, for this to happen GUPC must commit to an equal contribution of US$100m.